Arbitral Award Cannot Be Cut Down Merely Because the Amount Shocks the Court’s Conscience, Rules Supreme Court

Arbitral Award Cannot Be Cut Down Merely Because the Amount Shocks the Court’s Conscience, Rules Supreme Court in Marino Dredgeco v. Board of Trustees of the Port of Kolkata

Case: M/s Marino Dredgeco Limited v. The Board of Trustees of the Port of Kolkata
Citation: 2026 INSC 1238
Date of Judgment: 18 November 2026
Court: Supreme Court of India
Coram: Justice J. B. Pardiwala and Justice K. Vinod Chandran
Proceedings: Civil Appeal No. 14303 of 2026 with Civil Appeal No. 14304 of 2026 (arising out of SLP (C) No. 15175 of 2025)

Court Observation

“The words are not to be applied on a mere lip service and there should be a substantive reason which blatantly and patently brings forth the conflict with the most basic notions of morality or justice, resulting in the conscience of the Court being shocked.”

Summary

The Supreme Court has restored an arbitral award in favour of dredging contractor Marino Dredgeco Limited, holding that a court hearing an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 cannot cut down an award merely because the amount awarded seems too high to it. The Court set aside the Calcutta High Court Division Bench’s decision, which had halved the award and reduced the interest, on the ground that the claim for additional work exceeded 70 per cent of the original contract value and therefore shocked its conscience — even though the High Court had itself recorded that the award was based on adequate evidence and was not perverse, patently illegal or against the fundamental policy of Indian law.

The contractor was engaged in 1999 to dredge the approach channel and basin for a shore-based pilot station at Sagar Island. The work was delayed by force majeure conditions that were not the contractor’s fault, and repeated siltation made re-dredging necessary; the Port Trust entrusted the additional work by a letter of July 2000. The arbitrator’s award of November 2003 was upheld by a Single Judge under Section 34, but the Division Bench reduced the amounts to 50 per cent and the interest to 6 per cent from February 2002. The Supreme Court held that the modification could not be sustained, that the award could not be split into valid and invalid parts, and that there could be no interference with the quantum merely because the award debtor is a Government entity.

Key Holdings

  • A court exercising jurisdiction under Section 37 of the Arbitration and Conciliation Act, 1996 cannot set aside or modify an arbitral award merely by using expressions like “shocking the conscience of the Court”; the ground applies only where a substantive reason blatantly and patently shows a conflict with the most basic notions of morality or justice.
  • Where an award is supported by material on record, including measurements of pre-work and post-work levels, and is not perverse or patently illegal, a Section 37 court cannot re-appreciate the evidence or substitute its own view for the arbitrator’s.
  • Re-dredging to keep a channel and basin usable is the same work as the original dredging; the contractor’s claim for the additional work was, by the nature of the work, perfectly valid and not a windfall.
  • An award cannot be split into separate “valid” and “invalid” parts where the measurements and invoices are of one character, based on the same additional work of re-dredging; examining them would itself be an adjudication on the merits, which the Act prohibits.
  • There can be no interference with the quantum of a claim decided by the arbitrator on valid material merely because the award debtor is a Government entity and the quantum appears excessive without any substantiation.

Directions Issued

  • The Calcutta High Court Division Bench’s judgment modifying the award stands set aside; the contractor’s appeals are allowed and the arbitral award is restored.
  • The Port Trust’s appeal stands disposed of.

Background

By an agreement of June 1999, Marino Dredgeco was engaged to dredge the approach channel and basin for a shore-based pilot station at Sagar Island, for Rs 2,86,56,200, of which Rs 2,79,32,865 was paid for the original work. After 100 per cent siltation made repeated dredging necessary, the Port Trust entrusted the additional work in July 2000. The arbitrator awarded Rs 2,16,68,844 for the extra work and Rs 22,45,848 by way of refund of the security deposit, with interest at 10 per cent from 8 February 2002. A Single Judge of the Calcutta High Court upheld the award under Section 34 in January 2020, but the Division Bench, in September 2024, reduced the amounts to 50 per cent and the interest to 6 per cent, leading to the appeals before the Supreme Court.

Related Articles

Judgment Link: Read the full judgment (PDF)

Disclaimer: This is a summary prepared for informational purposes only and does not constitute legal advice. Readers should refer to the official judgment for the authoritative text.